ATLANTA –The bridge at Copeland Creek on FM 726 in Harrison County is scheduled to be replaced soon, according to plans awarded in August by the Texas Department of Transportation.

“During construction, the bridge will be closed, and traffic will be detoured,” said TxDOT Marshall Area Engineer Jacob Vise.

THK Construction, LLC of Longview was awarded the contract with a bid of $3,496,300.

 

Work is expected to begin November 27, 2023, and should take about seven months to complete.

 

Follow TxDOT’s Atlanta District on Facebook @TxDOTAtlantaTX, Instagram @txdotatlanta, X @TxDOTAtlanta and Nextdoor.

 

 

 

###

 

The Texas Department of Transportation is responsible for maintaining 80,000 miles of road and for supporting aviation, maritime, rail and public transportation across the state.

Connecting You with Texas

   www.txdot.gov  |  TxDOT on Facebook  |  TxDOT on Twitter

 

A Texas Department of Transportation (TxDOT) message

Leave a Comment