ATLANTA ­– A portion of Interstate 20 in Harrison County is scheduled for rehabilitation, according to plans awarded in June by the Texas Department of Transportation.

 

The 16.8-mile project will begin at the Gregg County line and extend 0.5 miles west of State Highway 43.

 

“This project will consist of drainage improvements along with some concrete pavement repair,” said Marshall Area Engineer Jacob Vise. “Work will take place in both east and westbound lanes of Interstate 20,” he added. The roadway will be limited to one lane in certain areas while work is underway.

 

GHB Equipment Company, L.L.C. of Bonham was awarded the project with a low bid of $4,714,765.

 

The project is expected to begin in August and is scheduled to take about 13 months to complete, weather permitting.

 